CHA Home Page

 




 



Update on Project and Action Items

Go to Project History and CHA Concerns

Go to the Media Alert/Resolution to Board of Supervisors
Go to How to Get Involved
Go to Reponse to PG&E Letter
Go to Flyer to Cow Hollow Neighbors - Dec. 19, 2003

View EMF Fact Sheet
View Route Options

Project Update (as of July 2004)

The main feeder along Filbert is now energized and was finally switched on via one of the newly installed, underground "primary" switches located in the sidewalk at the northeast corner of Filbert at Divisadero. PG&E "heated up" the entire feeder from the substation on Bay Street, and did not have to use that new overhead "riser" tap in front of the Cow Hollow Woodworks on Steiner at Filbert as an interim connect point as we surmised.

As expected, when PG&E energized the feeder, the EMF readings registered an initial increase along the Filbert portion of the feeder to an average range of .8 to 1.4mG. Some areas at key locations (i.e. over underground switches, etc.) are higher, but the fairly low initial readings are in line with what we predicted and that is encouraging. Initially "energizing" the new Lucas Feeder has not significantly added to the existing EMF along North Filbert/East Lyon, but the line is very minimally loaded now. We need to carefully monitor any changes as the Lucas load is steadily increased over the next several months.

The windows at the Lucas buildings 1-4 are almost all installed and I'd expect their electrical contractor to begin testing the "permanent" electrical system very soon. They will generally leave a majority of the lights, etc. on to test the systems and we'll try to get another full set of measurements along the feeder to coincide with the increased load. The large, temporary transformers being used for all of the "temporary construction service" to the Lucas site are still in place and remain functional. Apparently, they are not yet being supplied from the new main feeder.

The other "riser tap" (and transfer switch) at the intersection of Lyon and Greenwich is still not complete and the large set of 3 -1100kcm Aluminum cables are coiled on the pole. Curiously, this existing wooden pole already has a riser on it, which is, presumably, one of the existing main primary feeds for the Presidio. It will be interesting to see when/if this existing feed is removed, as combining two feeders and switches on a single pole like that is generally not considered the best design for prudent "outage prevention".

Also, along those lines, this "key" riser pole is directly at the end of Greenwich and Lyon. This is a "T" intersection for vehicle traffic and is also a tight left turn and stopping point for the quite frequent #45 & #41 Muni Buses. Any unfortunate accident involving the pole could leave the existing neighborhood exposed to a prolonged power outage. With 2500-3000 new workers expected at Lucas and all the new auto traffic that will result, perhaps the wisdom of designing a key "riser" switch on this rather vulnerable pole should have been more carefully considered by PG&E.

The pad mounted "capacitor" (and its switch) is installed just inside the Presidio wall on Lyon just North of Filbert and is now operational and buzzing like crazy. Also, a realtor from Hill & Co. did confirm to me that the plan is for the Letterman Digital Arts Center buildings to be "1/3" subleased.

Attached are a few photos of that "riser" mentioned above at Lyon/Greenwich the first one shows the specifications including the "25KV" rating.

Project Update (as of April 2004)

PG&E has now completed the trenching and installation of the conduit for the Lucas Powerline along North Point-Bay-Fillmore-Filbert-Lyon, but Concerned Neighbors on Fillmore, Filbert, and Lyon Streets and the Cow Hollow Association will continue to advocate for the residents and small business owners in Cow Hollow, no matter how long it takes.

The ill-conceived electric distribution project through a densely populated neighborhood to serve an industry located inside the federal Presidio national park, Lucasfilm Ltd.'s Letterman Digital Arts Center (LDAC), is a result of PG&E's poor planning, the Presidio Trust's passive disengagement, and the past unwillingness or inability of City agencies to exercise effective oversight. We continue our written and personal contact with the California Public Utility Commission, PG&E, Lucasfilm Ltd., the Presidio Trust, Department of Public Works, Mayor Gavin Newsom, San Francisco Supervisors, and the Media.


The Concerned Neighbors on Fillmore, Filbert, and Lyon Streets are requesting the following:

CPUC
1. Conduct a one-day hearing before a PUC examiner to review and discuss the Powerline and alternatives to the route.

2. Conduct an audit to insure that the most advanced and protective shielding and wire configuration techniques will be utilized along the right of way for the Lucas Powerline.

3. Stop work on the Lucas Powerline Project before any wire is installed in the conduits on the grounds that PG&E has failed to coordinate with the City and County of San Francisco as called for in Board Resolution 817-03 (We have made a formal written request to the CPUC on February 20, 2004).

PG&E
1. Stop replying to our requests for specific, technical information with vague, uninformative
and/or evasive answers.

2. Hold a public meeting, along with Lucasfilm Ltd. to allow for open review and public participation in the planning of the selected route and consideration of alternatives, the study of public health and safety issues, and the mitigation of such risks. Given the proximity of the Project's powerlines to homes (many of which are occupied by young children), shops and a school, and the lack of any public information regarding alternatives or mitigation measures, we feel we have raised legitimate concerns as to public safety. PG&E has ignored our repeated requests and the City and County of San Francisco's Board of Supervisors Resolution 817-03 (Unanimously adopted by the Board on December 16, 2003, approved and signed by Mayor Brown on December 19, 2003, and supported by the Cow Hollow Association) for:

  • Lucasfilm Ltd. and Pacific Gas & Electric Co., Inc. to work with the community on alternatives to its Bay-Fillmore-Filbert-Lyon route for supplying power to the Letterman Digital Arts Center in the Presidio..."
  • "To ensure the route for the powerlines servicing Letterman Digital Arts Center involves as little impact to the community as possible..."
  • "To select the route that best protects the health and safety of San Francisco's residents.


3. Coordinate an audit by the CPUC to insure that the most advanced and protective shielding and wire configuration techniques will be utilized along the right of way for the Lucas Powerline. At the 1/15/04 Safety Meeting with DPW, PG&E, UCC, SFPD, and neighbors, PG&E's Project Manager Gary Tognozzi offered to have PG&E coordinate the CPUC audit after we asked questions about what is actually going to be placed in the street.

4. Re-locate the "splice box" on Filbert Street at Broderick from the sidewalk onto the street, as all the other boxes were installed.

Lucasfilm Ltd.
1. Hold a public meeting, along with PG&E.

2. Explain why Lucasfilm Ltd. hired PG&E to provide all of its electricity, instead of pursuing "greener" alternatives.

3. Explain why Lucasfilm Ltd., when made aware of the community's concern with the powerline, took no steps to put the Project on hold so that alternatives could be considered.

Presidio Trust
1. Create an Energy Master Plan for the Presidio that is in keeping with the national park's "green" principles of new construction, including in-house and alternative sources of power, limiting traditional energy sources, and energy conversation.

2. Disclose why the Environmental Impact Statement prepared for the Park and the Lucasfilm Ltd. Center (LDAC) did not include the Centers electrical requirements.

3. Construct the needed electrical capacitor(s) in the Presidio vs. San Francisco, as has been indicated would occur.

DPW
1. Re-write the Public Works Code to address new feeder line construction (vs. upgrading/rehabilitating existing wiring) through existing densely populated neighborhoods - public notice, participation, disclosure of facts, and mitigation of health and safety risks.

2. Insure that construction projects of this magnitude are conducted safely, eliminating the need for citizens to request inspections and safety meetings.

Mayor Newsom
Continue the good work he started by sponsoring the Resolution 817-03 to bring PG&E and Lucasfilm Ltd. to the table and meet with the impacted residents and small business owners.

SF Supervisors
Pressure PG&E and Lucasfilm Ltd. to follow the adopted Resolution 817-03 and participate in a public meeting to discuss with the residents and small business owners in Cow Hollow the planning and future impacts of the Lucas Powerline.

Media
Encourage them to investigate and cover the Lucas Powerline story.

Our basic questions still remain, which include:

· How was the selected route chosen over other potential routes, noting that the substation is one block from the northern waterfront and open space that connects directly with the Presidio?
· Why did the Presidio Trust EIS exclude the Letterman Digital Arts Complex electrical requirements?
· Where is the Presidio Trust's short and long term Energy Master Plan?
· Why are the City of SF and its residents bearing the brunt of the energy project serving the federal government's national park?

For those in Cow Hollow on the Lucas Powerline (Lyon, Filbert, Fillmore):
Please contact PG&E's Bill Gray at 925.866.5386 and have the EMFs (Electric and Magnetic Fields) measured in and around your residence, considering these locations only:
· the street facing rooms of your house
· the front yard measured at the front building wall
· at the edge of any planter
· at the curb
Please email your results to: brookesampson@yahoo.com

To learn more about the Lucas Powerline, check our website at http://www.cowhollowassociation.org/Lucasnewsletter.shtml and send an email to stoppge@yahoogroups.com